~ Naperville residents can expect some changes to their daily commute as the City of Naperville begins a major water main replacement project on Ogden Avenue and Washington Street. According to a press release from the city, motorists should anticipate lane reductions and increased travel times starting the week of May 18.
The project, which is expected to continue through October 2026, will involve replacing the aging water main on Ogden Avenue between Washington Street and Wright Street, as well as on Washington Street between Ogden Avenue and Bauer Road. This work is necessary as the existing cast iron water main pipe, installed in the 1950s and 1960s, has reached the end of its useful life.
The first phase of this project began in spring 2025 but was temporarily paused during the fall and winter months. However, crews will now resume work to replace the old water main with a new upsized 16" pipe in accordance with City standards. This will also include replacing water valves, hydrants, and services along the length of the water main.
A second phase of similar work is scheduled to begin in early summer on Ogden Avenue between Washington Street and Naper North High School. This phase aims to continue improvements made in the first phase and enhance system reliability. The city assures that additional details about this work and related traffic impacts will be shared in advance.
More on illi News
As work progresses, motorists can expect ongoing lane closures and traffic pattern changes. Crews will typically work from Monday through Friday from 7 a.m. to 3:30 p.m., with occasional extensions until 5 p.m. Motorists are advised to use caution, follow posted signage, exercise patience, and allow for extra travel time when passing through these areas. There may also be occasional disruptions to water service; however, residents will be notified proactively by crews.
This project is just one of several underway by Naperville Water Utility over the summer to replace aging water mains. These replacements aim to reduce water main breaks, increase water flow and service reliability, lower maintenance costs, and extend the life of the system. More information about these ongoing projects can be found on the city's website.
For more information on the City of Naperville, residents can visit www.naperville.il.us. They can also sign up for Naper Notify, the city's notification system that provides important updates via phone calls, text messages, emails, or a smartphone app. This includes traffic alerts and other important information. To sign up, visit www.napernotify.com.
The project, which is expected to continue through October 2026, will involve replacing the aging water main on Ogden Avenue between Washington Street and Wright Street, as well as on Washington Street between Ogden Avenue and Bauer Road. This work is necessary as the existing cast iron water main pipe, installed in the 1950s and 1960s, has reached the end of its useful life.
The first phase of this project began in spring 2025 but was temporarily paused during the fall and winter months. However, crews will now resume work to replace the old water main with a new upsized 16" pipe in accordance with City standards. This will also include replacing water valves, hydrants, and services along the length of the water main.
A second phase of similar work is scheduled to begin in early summer on Ogden Avenue between Washington Street and Naper North High School. This phase aims to continue improvements made in the first phase and enhance system reliability. The city assures that additional details about this work and related traffic impacts will be shared in advance.
More on illi News
- FrostGuard Introduces Innovative Inflatable Window Well Insulation System
- Chicago: Mayor Brandon Johnson Joins Resident Association of Greater Englewood to Break Ground on The Re-up at 59th And Racine
- Chicago: Mayor Brandon Johnson Breaks Ground on C.A.R.E. Manor, Bringing 44 Affordable Homes Designed for Multi-Generational Living to West Garfield Park
- Advancing High-Potential Nevada Critical Minerals Portfolio as Major Drill Program Nears Assay Results: Glenstar Minerals: Stock Symbol: GSTRF
- Midwest Pond Features & Landscape Urges Mid-June Pond Maintenance as Summer Algae Risk Rises
As work progresses, motorists can expect ongoing lane closures and traffic pattern changes. Crews will typically work from Monday through Friday from 7 a.m. to 3:30 p.m., with occasional extensions until 5 p.m. Motorists are advised to use caution, follow posted signage, exercise patience, and allow for extra travel time when passing through these areas. There may also be occasional disruptions to water service; however, residents will be notified proactively by crews.
This project is just one of several underway by Naperville Water Utility over the summer to replace aging water mains. These replacements aim to reduce water main breaks, increase water flow and service reliability, lower maintenance costs, and extend the life of the system. More information about these ongoing projects can be found on the city's website.
For more information on the City of Naperville, residents can visit www.naperville.il.us. They can also sign up for Naper Notify, the city's notification system that provides important updates via phone calls, text messages, emails, or a smartphone app. This includes traffic alerts and other important information. To sign up, visit www.napernotify.com.
0 Comments
Latest on illi News
- STO Foundation Launching June 29, 2026 to Advance the Global Tokenization Industry
- West Virginia Leaders Announce Support for Election Integrity Network's Model Election Laws Handbook
- CCHR Condemns Behavioral Treatment After FDA's Missed Deadline to Ban Shock Device
- Naperville: Special Citywide Brush Collection Taking Place Beginning Week of June 15
- Brilliant Minds to Gather in Fort Worth for National Mensa Event
- UK Financial Ltd Completes One Of The Most Extensive CoinMarketCap Supply Verification Packages For Maya Preferred PRA (MPRA)
- Data Tiles Strengthens U.S. Presence with Chief Revenue Officer John Goode
- Haven Media Solutions Offers Web Design and PPC Services in Atlanta GA
- Actress Zaria Imani Primer Marks Final Season of The Chi with Full-Circle Moment
- A Seat for Everyone: Naperville Comes Together
- TREND Network Announces Miami Based Reality Series "Coming Up Miami" Premiering July 1
- Beemok Hospitality Collection And KLH Group Announce Preferred Partnership
- Inkdnylon Expands Wholesale Brand Customization Program for Branded Apparel, Company Stores, and Promotional Products
- Expanding Access to Mental Health Care in Toronto with Dr. Stephen Shainbart
- Dr. Stephen Shainbart Launches Expanded Mental Health Support for Anxiety and Depression in Toronto
- Equipment Leases, Inc. Launches Updated Family Office Equipment Financing Page
- The $5 Million Man Still Begging: Incumbent Jimmy Panetta Hits Up Voters for More Cash Despite Massive War Chest
- Kevin Francis Design Introduces CHROMA, a Collection of Saturated Solid Color Wool Rugs
- Hardwood Floor Refinishing Services That Transform Spaces and Restore Lasting Beauty
- AI ROI Calculator Launches AI Transformation Intelligence Platform to Help Organizations Identify, Prioritize, and Measure AI Opportunities